Hoffman Estates

Printer-friendly versionPrinter-friendly versionSend to friendSend to friend

Construction Projects
Location: Around Shoe Factory Road
Start Date: Oct. 18, 2010
Completion Date: Spring 2012

Construction on the Sutton Siding extension began Oct. 18, 2010. The project will extend the existing Sutton Siding track south, through the Shoe Factory Road grade crossing. Work on this project is primarily complete. Some minor close-out items will continue into the spring of 2012.

Location: Shoe Factory Road 
Start Date: December 2010
Completion Date: End of 2011

An advance warning sign is being installed along Shoe Factory Road which will alert westbound motorists that traffic will be stopped ahead.